Management Area:
North Fraser
Parks:
Sasquatch Park
Term:
5 years
Summary of Activity:
Temporary detour construction/Clearing and Grubbing/Grading Work including excavation, backfill, subgrade and base construction for roadway/Asphalt Paving/Temporary abutment and temporary bridge installation and removal/Detour roadway removal
? Reinstatement
? Vegetation including replanting
Permanent riprap installation in the Trout Lake creek
? Minor Channel excavation
? Riprap installation
? Habitat features improvement
Temporary traffic flow through Park during construction
Permit Type:
Permittee:
His Majesty The King in right of the Province of British Columbia as represented by the Ministry of Transportation and Infrastructure