113092

Management Area: 
Omineca
Parks: 

Giscome Portage Trail Protected Area

Term: 
3 years
Summary of Activity: 
The 19.9 km NPS 42 CS4A-CS4B Upstream Pipeline loop construction by contractor will include: • Installation of a 1067.0 mm OD steel natural gas pipeline from approximately C-41-B/93J7 to D-40-H/93J2. This translates to KP0+000 to KP19+700. The Giscome Portage Trail will be open cut. Remediation and reclamation of lands following construction.
Permit Type: 
Permittee: 
WESTCOAST ENERGY LIMITED PARTNERSHIP
Issue Date: 
Friday, August 14, 2026
Region: